Bankable competitive procurement frameworks provide a credible and repeatable route for converting identified infrastructure needs into financeable projects. They bring together structured competitive tendering, clear qualification and evaluation criteria, standardized contractual arrangements and explicit allocation of risks between public authorities, utilities, developers and lenders. Unlike stand-alone contracting mechanisms, these frameworks cover the pathway from defining the required project and inviting competition to establishing the long-term revenue arrangements needed to reach financial close.
Competitive bidding can support price discovery and cost discipline, while long-term revenue arrangements, such as power purchase agreements or availability-based contracts, provide greater certainty over future cash flows. This combination can reduce development and financing risk, broaden participation among domestic and international investors and strengthen confidence that projects will proceed on clearly defined terms. The approach is particularly relevant where investment appetite exists but projects lack a credible route to market or a sufficiently predictable revenue model. Such frameworks are widely used for renewable generation and can also be applied, with asset-specific contractual structures, to storage, transmission and other strategic power infrastructure. When applied across successive procurement rounds, they can create a visible project pipeline, allow documentation and processes to be refined over time and support delivery at scale.
Main Outcomes of the Solution
Key implementation and scaling factors
Case study
Dubai Electricity and Water Authority (DEWA) (2012 - ongoing), United Arab Emirates
Dubai Electricity and Water Authority (DEWA) has used an independent power producer (IPP) procurement framework to develop successive phases of the Mohammed bin Rashid Al Maktoum Solar Park, which was launched in 2012. The 200 MW second phase, inaugurated in 2017, was the first phase developed under the IPP model, combining competitive procurement with long-term contractual arrangements.
DEWA continued this approach for subsequent phases. For the 1,800 MW sixth phase, it launched the procurement process in September 2022, receiving 23 expressions of interest and subsequently prequalifying seven international bidders. Masdar was selected as preferred bidder in 2023 for the project, with investment of up to AED 5.51 billion (USD 1.50 billion as of Sep 2026). The project reached financial close in February 2024.
DEWA subsequently initiated procurement of the seventh phase under the IPP model, reporting expressions of interest from50 international companies in April 2025, subsequently prequalifying 10 international bidders. The project has now progressed to the bid evaluation stage.The successive procurement rounds illustrate how a repeatable competitive framework, combined with long-term revenue arrangements, can provide a defined route to market and mobilize private investment for large-scale renewable generation.