Cap-and-floor investment frameworks support long-duration electricity storage by reducing revenue uncertainty while preserving market-based operation. Under this model, storage assets continue earning revenues from electricity market activities, but a regulated floor provides minimum revenue protection if market earnings fall below an agreed threshold, while a regulated cap limits excess revenues and can return upside value to consumers. This creates a clearer investment case for storage assets that have high upfront costs, long development timelines and uncertain future market revenues.
Long-duration electricity storage can provide flexibility over extended periods, helping shift surplus renewable generation, manage periods of low renewable output, support security of supply and reduce reliance on fossil-fuel-based backup or balancing resources. However, many long-duration technologies face financing barriers because their full system value is not always captured through short-term wholesale or ancillary service markets. A cap-and-floor framework helps address this gap by creating a bankable revenue structure, while still incentivizing projects to operate efficiently in the market.
Main Outcomes of the Solution
Key Deployment and Scaling Factors
Case study
Ofgem Long Duration Electricity Storage Cap-and-floor Scheme (2025), United Kingdom
Ofgem is implementing a cap-and-floor scheme to enable investment in long-duration electricity storage while protecting consumers. Under the model, Ofgem sets a minimum and maximum level of revenue for an LDES project: when revenues fall below the floor, consumers top up the difference through energy bills; when revenues exceed the cap, the extra money is returned to consumers through reductions in network charges. Ofgem states that this model encourages investment by guaranteeing revenues that can offset high upfront costs and market uncertainty for LDES projects.
The first application window is structured around two streams. Stream 1 applies to more mature technologies, requiring at least 100 MW of capacity and TRL 9. Stream 2 supports less mature technologies, requiring at least 50 MW of capacity and TRL 8. Both streams must be able to discharge continuously at full power for at least eight hours. The scheme responds to a clear system need: Ofgem identifies an indicative capacity range of 2.7–7.7 GW of additional LDES required by 2035, based on NESO advice.
The case shows how a regulated investment framework can improve bankability for long-duration storage, while using eligibility thresholds, cost-benefit analysis and consumer-protection mechanisms to support system flexibility and security of supply.