Capital-intensive clean energy assets, such as nuclear power, large grid expansions, long-duration storage, carbon capture facilities and industrial decarbonization hubs, require substantial upfront capital, long payback periods and stable policy frameworks. Global energy investment is projected to reach about USD 3.3 trillion in 2025, with roughly USD 2.2 trillion flowing into clean energy technologies.[1] This level of spending reflects strong momentum across solar, storage, grids and electrification, yet investment remains concentrated in advanced economies, while many emerging and developing markets continue to face limited access to affordable capital. High financing costs, currency exposure and construction risk still constrain long-lived clean energy infrastructure, particularly in regions where system demand is growing fastest. These barriers slow deployment of firm low-carbon technologies that are important for system reliability.
Financing models that combine public and private capital help improve bankability and reduce financing costs. Regulated Asset Base frameworks, blended finance structures, credit enhancement tools and multi-stakeholder ownership arrangements share risks across governments, utilities, investors and consumers, while creating more predictable long-term revenue streams. By improving investment certainty and mobilizing institutional capital, these structures support the scale-up of firm low-carbon technologies and the delivery of critical infrastructure for a resilient and affordable net-zero energy system.
Main outcomes of the solution
Key deployment and scaling factors
Case Study
Sizewell C and United Kingdom Government (2025), United Kingdom
In 2025, Sizewell C secured a Final Investment Decision under a Regulated Asset Base (RAB) financing model that combines public and private capital. The structure allows regulated returns during construction and shares financing risk among the government, the developer, consumers, and private investors. The project comprises two European Pressurised Reactor (EPR) units with a combined capacity of approximately 3.2 GW, replicating the design used at Hinkley Point C. Once operational, Sizewell C is expected to provide long-term, low-carbon electricity, supplying power equivalent to that used by around six million homes over its operating life.
The financing package combines government equity with private investment from La Caisse de dépôt et placement du Québec, EDF, Centrica and Amber Infrastructure, supported by long-term debt from commercial lenders and national and export-credit agencies. The project includes extensive domestic participation, with more than 70% of contract value awarded to UK businesses and a large workforce engaged during peak construction.[2,3]
Solution and insights developed with contributions from the World Nuclear Association.