There is currently no known example of this form of development being applied specifically to PNT systems; however, similar approaches have been successfully implemented in other domains, such as Earth Observation, and could serve as a useful reference.
Prerequisites:
• Strong political mandate and sustained funding
• Spectrum/ITU coordination and filings and regional regulatory framework
• Partnerships with established GNSS/space primes and launch providers
• Technical Infrastructure (Servers and Storage, Network, GNSS Receivers)
• Technical expertise for system development, integration and operations
• Cybersecurity, data protection, and continuity planning
• Legal/regulatory framework for managing and sharing PNT data.
• Procurement pathway
• Partner support as needed
Cost:
• Ballpark: USD 5–10 B (shared among partners)
• Includes: governance framework and cost-sharing agreements, constellation design and architecture, satellite procurement and AIV (assembly, integration & verification), launch services and insurance, ground control and monitoring infrastructure, navigation signal design and authentication, international certification (ICAO/IMO/ITU), training and technology transfer, long-term operations and replenishment
Timeframe:
•Overall: 84–120 mo (7–10 years)
• Phases: scoping/partnership negotiation (12–18 mo), design/prototyping (18–24 mo), satellite production & ground segment development (24–36 mo), launches & integration (12–24 mo), operations (ongoing with OPEX)
Pros:
• Leveraging Shared Resources - Access to capabilities at a lower cost
• Driving Cooperation - Fosters international collaboration
Considerations:
• Dependency - Reliant on external providers
• Technology Transfer - Constraints can arise from the technology transfer set up