Projet Mauricie is a large-scale renewable hydrogen project located in Shawinigan and the wider Mauricie region, Canada. This projet will use a combination of baseload hydroelectricity, and 1 GW of wind and solar power, behind the fence, self-production, to feed a ~ electrolyzer.. The facility is designed to produce up to 70,000+ tonnes of green hydrogen annually by 2030. A third of the hydrogen will serve to decarbonize heavy mobility applications, while the remaining part will be converted into synthetic natural gas for injection into the provincial gas grid. The project will abate emissions by around 800,000 tonnes of CO₂ equivalent per year, a first of its kind at such scale in the province.
Objective & Results
- Deliver green hydrogen to Québec’s industries/sectors that are hard to electrify (heavy transport and industry) exclusively within the province
- Enable production of renewable gas (e-NG / renewable methane) from part of hydrogen output to help decarbonize industrial gas uses
- Leverage Québec’s renewable electricity baseload complemented with greenfield behind-the-mater renewable assests.
- Stimulate regional economic growth, job creation, value retention within Québec
Lessons Learned
- A diverse renewable energy mix, hydro from the grid, and wind and solar behind-the-fence, ensures a stable and competitive power supply.
- Regulated policy targets, such as Québec’s 10 % renewable gas distribution objective by 2030, provide demand visibility and support financing.
- Local offtakers in industry and transport reduce dependence on export markets.
- Land use, permitting and community consultation are critical to project acceptance.
- Environmental attribute monetization is necessary to narrow the gap with fossil fuels.
Key Metrics
- Green hydrogen capacity: 60,000+ tonnes per year
- CO₂ emissions avoided: ~800,000 tonnes annually
- Renewable energy buildout: 1 GW (behind the meter) wind and solar farm to complement 150MW baseload from the grid
- Split of output: ~ one-third to decarbonize long-haul transport; remainder to e-NG / gas applications
- Jobs (direct): >1,700 during construction; ~200 permanent post-COD